| Service
and Meter Installation Requirements Guide 04.35 SERVICE TO MULTIPLE NON-RESIDENTIAL BUILDINGS When a group of separate, nonresidential buildings are to be served by a single three-phase padmounted transformer, a main disconnect will be required before the meter(s) on each building. This provision shall apply even when there are six or less meter positions at each location. Without the main disconnects on each building, all the buildings would have to be taken out of service for work to be done on any individual building's service entrance facilities. End of Specification:
|
|||||||||||||||